By Jeryl L. Olson, Kay R. Bonza, and Craig B. Simonsen
Seyfarth Synopsis: New Illinois Office of State Fire Marshall (“OSFM”) regulations, (42 Ill. Reg. 10476, 10662-667, June 15, 2018, effective October 13, 2018), require that periodic operation and maintenance include recorded “walkthrough inspections” for underground storage tank (UST) facilities.
Under new OSFM rules, each Class A Operator, who has the primary responsibility of operating and maintaining the UST system, and Class B Operator, designated with day-to-day aspects of operating, maintaining and recordkeeping for UST systems “… shall perform walkthrough inspections of each storage tank system for which he or she is designated, and shall record the results of each inspection on a checklist to be maintained with the facility records.” The walkthrough inspection requirement took effect on October 13, 2018, and replaces the previous requirement to conduct quarterly equipment inspections. The rules under Part 35, Section 176.655 of the Illinois Administrative Code, require that at a minimum, a walkthrough inspection shall be conducted at least once every 30 days and include inspection of:
- Release detection methods, including monitoring systems and all associated sensors;
- The integrity of spill and overfill prevention and spill containment equipment and manholes;
- Dispensers, hoses, breakaways and hardware for leaks and damage; and
- Operational status of impressed current cathodic protection systems, including checking and recording that the power is on and that the voltage, amps and hour meter have the appropriate readings required under Section 175.510(f), with a log entry that shows date of inspection, initials of inspector, hour, volt and amp readings, and power on verification.
In addition, at least once per year the Operator shall inspect:
- All containment sumps by: (i) checking for visual damage to the sumps, covers and lids; (ii) checking for the presence of regulated substances or any indication that a release may have occurred; and (iii) checking that the sumps and the interstitial areas for any double-walled sumps with interstitial monitoring are free of water, product and debris;
- All UST equipment including emergency stops for the presence or absence of visible damage to any UST component;
- Emergency stops to document they have been tested by the owner/operator or a contractor for interconnection and pump shutdown;
- Shear valves to document they have been visually inspected by the owner/operator or a contractor;
- All required signs to ensure they are fully visible and all communication systems in place and operational;
- All daily, 30-day, monthly and annual inspections, testing, reporting and records required under 41 Ill. Adm. Code 174, 175 and 176; and
- If applicable, the tank gauge stick or groundwater bailers, for operability and serviceability (manual tank gauging or groundwater monitoring).
To assist owners and operators with rule compliance and recordkeeping requirements, the OSFM provides a UST Operations and Maintenance Plan Template Form (OSFM O&M Plan Template). As noted in the OSFM O&M Plan Template and in the rules, each Class A or Class B Operator “shall perform walkthrough inspections” of each storage tank system for which they are designated and shall record the results of each inspection “on a checklist to be maintained with the facility records.” Specific 30 day inspection report forms and annual walkthrough inspection report forms are also available from the OSFM. The OSFM also provides FAQs For Class A, B, and C Operator Training.
For more information on this or any related topic please contact the authors, your Seyfarth attorney, or any member of Seyfarth’s Environmental Compliance, Enforcement & Permitting Team.